industry

High-rise production unit

Customer:

Solutia Europe Bvba

Architect:

Grontmij Industry Nv - Zelzate

Construction period:

aug 2013 - mrt 2015

Construction task:

2.808.629

Location:

Gent

About the project

The Process Tower on the Solutia site in Ghent is 24 metres-tall and constructed in the centre of a lower production building. Site organisation was prepared in detail together with the client to keep the effect on production to a minimum.
The works include structural work and finishing.

Key figures

Construction surface  200 m² 
No. floors